Delhi High Court Upholds Release of Rs 9.3 Crore Bank Guarantee and FDR Interest to Jaksons Developers in DDA Hotel Dispute

Date:

New Delhi: The Delhi High Court has dismissed an appeal by the Delhi Development Authority (DDA) and upheld a single judge’s order under which interest accrued on a fixed deposit made from an encashed Rs 9.3 crore performance bank guarantee must go to Jaksons Developers, along with the guarantee amount itself. A bench of Justices Dinesh Mehta and Aditi Choudhary passed the judgment on November 6 in DDA v. Jaksons Developers (P) Ltd (FAO(OS) (COMM) 192/2026), after reserving it on October 13.

The dispute arose from commercial plot 3B1 at Twin District Towers, Rohini, which DDA put up for bids for a hotel to provide accommodation for the 2010 Commonwealth Games. Jaksons Developers was the successful bidder and was issued an allotment letter on January 4, 2008, with the hotel to be made operational within 24 months. It furnished a performance bank guarantee of Rs 9.3 crore, 5% of the bid amount.

In 2010 DDA moved to invoke the guarantee for non-completion within 24 months. Jaksons got interim protection from the High Court, and later, on an application before the arbitrator, the guarantee was allowed to be encashed with the amount kept in a fixed deposit that, along with interest, would abide the outcome. The court noted that the hotel was made operational on September 15, 2010, before the Games, and was used during the Games.

The arbitrator’s April 25, 2023 award held that DDA was not entitled to invoke the guarantee and directed release of the Rs 9.3 crore, rejected DDA’s counter-claims, but declined interest on the awarded amount and, by an addendum, directed that the interest on the fixed deposit not be released. A single judge on May 5, 2026 set aside that part of the award, holding that the interest was the fruit of the principal amount.

Agreeing with the single judge, the Division Bench said the interest on the fixed deposit is nothing but the fruit of the principal and, since the principal was ordered to go to Jaksons, the interest should follow. It held that the directions on the guarantee amount and the interest were severable and that there was no reason to interfere. The appeal and pending applications were disposed of.